Biomass Plants Cramlington and Kent

The CRAMLINGTON and KENT power plants are newly built renewable energy facilities in the UK. The plants are 100% biomass and wood chip fired and generate 27.7MW of electricity.
The boiler is designed to produce a live steam flow of 25.0 kg/s at 140 bar(g) and 540° C. The furnace consists of 4 parallel working feeders and a water-cooled vibrating grate.
An oil-fired furnace is used for start-up of the boiler and as auxiliary firing.
Lindner carried out insulation work on a surface of 8,500 m²  for each project in the two identical power plants. The insulation included the thermal and sound insulation of the flue gas, hot air and cold air ducts, the boiler as well as all piping and components with wired mats and trapezoidal steel sheets.

img_uk_cramlington_kent_1
img_uk_cramlington_kent_2
img_uk_cramlington_kent_3
img_uk_cramlington_kent_4
img_uk_cramlington_kent_5

General

Project: Biomass Plants Cramlington and Kent

Building Type: Power Plants

Zip/City: NE23 Cramlington/ Kent

Country: United Kingdom

Completion: from 2017 to 2018

Company: Lindner Isoliertechnik & Industrieservice GmbH


Companies involved

Operator: Cramlington Renewable Energy Developments / BWSC

Operator: Kent Renewable Energy Partnership / BWSC

Client: Baumeister & Wain Scandinavian Contractor A/S


Products

Insulation Engineering

17000 sqm


References

Our Projects worldwide

Once around the globe and back again to our home Arnstorf: With our construction projects we are represented almost everywhere! No matter whether new construction or renovation, whether interior fit-out, building envelope or insulation – our references consist of a colourful mixture full of new challenges and impressive results.